Wongm's Rail Gallery » Abbotts Road level crossing removal project

Abbotts Road level crossing removal project

The level crossing on the Cranbourne line at Abbotts Road in Dandenong South is being replaced by a single track rail over road bridge

Time lapse camera pointed at the bridge, mounted to a neighbouring building

30 September 2018 16:50 PM
Viewed 65 times
(4 times this month, 65 times this year)

Damaged overhead stanchion still tied back with temporary steel cables to concrete blocks

30 September 2018 16:50 PM
Viewed 113 times
(6 times this month, 113 times this year)

'Boom gates gone' propaganda on the approach to the completed bridge over Abbotts Road

9 September 2018 11:36 AM
Viewed 93 times
(1 time this week, 1 time this month, 93 times this year)

Looking west past the completed bridge over Abbotts Road

9 September 2018 11:36 AM
Viewed 96 times
(3 times this week, 2 times this month, 96 times this year)

Damaged overhead stanchion tied back with steel cables to concrete blocks

9 September 2018 11:34 AM
Viewed 82 times
(1 time this week, 1 time this month, 82 times this year)

Traction power feeders to the Hampton Park tie station

9 September 2018 11:34 AM
Viewed 116 times
(3 times this week, 2 times this month, 116 times this year)

Damaged overhead stanchion tied back with steel cables to concrete blocks

9 September 2018 11:33 AM
Viewed 120 times
(2 times this week, 2 times this month, 120 times this year)

Concrete blocks and steel cables reinforced a damaged overhead stanchion

9 September 2018 11:33 AM
Viewed 133 times
(3 times this week, 3 times this month, 133 times this year)

Cantilevered concrete pillar cracked due to the forces imposed by the overhead stanchions bolted to the top

9 September 2018 11:33 AM
Viewed 159 times
(4 times this week, 4 times this month, 159 times this year)

Concrete blocks and steel cables reinforced a damaged overhead stanchion

9 September 2018 11:33 AM
Viewed 80 times
(3 times this week, 2 times this month, 80 times this year)

Damaged overhead stanchion tied back with steel cables to concrete blocks

9 September 2018 11:32 AM
Viewed 70 times
(2 times this week, 1 time this month, 70 times this year)

Damaged overhead stanchion tied back with steel cables to concrete blocks

9 September 2018 11:31 AM
Viewed 74 times
(2 times this week, 2 times this month, 74 times this year)

Overhead stanchions bolted to the side of the concrete viaduct

9 September 2018 11:31 AM
Viewed 96 times
(1 time this week, 1 time this month, 96 times this year)

Looking east past the remains of the level crossing beside the bridge at Abbotts Road

9 September 2018 11:30 AM
Viewed 90 times
(3 times this week, 3 times this month, 90 times this year)

Remains of the level crossing beside the bridge at Abbotts Road

9 September 2018 11:30 AM
Viewed 81 times
(1 time this week, 1 time this month, 81 times this year)

Underground traction power feeders to the Hampton Park tie station

9 September 2018 11:30 AM
Viewed 98 times
(1 time this week, 1 time this month, 98 times this year)

Remains of the level crossing beside the bridge at Abbotts Road

9 September 2018 11:30 AM
Viewed 88 times
(2 times this week, 2 times this month, 88 times this year)

Looking north along the new bridge from Abbotts Road

9 September 2018 11:29 AM
Viewed 87 times
(3 times this week, 2 times this month, 87 times this year)

Looking south past the remains of the level crossing beside the bridge at Abbotts Road

9 September 2018 11:29 AM
Viewed 73 times
(2 times this week, 2 times this month, 73 times this year)

Looking north along the new bridge from Abbotts Road

With space for a second track on the former alignment of the ground level track

9 September 2018 11:29 AM
Viewed 74 times
(1 time this week, 1 time this month, 74 times this year)

Looking south past the remains of the level crossing beside the bridge at Abbotts Road

9 September 2018 11:29 AM
Viewed 83 times
(1 time this week, 1 time this month, 83 times this year)

Looking north along the new bridge from Abbotts Road

9 September 2018 11:29 AM
Viewed 88 times, 88 times this year)

Single 'U' trough section in place over Abbotts Road

14 July 2018 11:31 AM
Viewed 164 times
(1 time this week, 1 time this month, 164 times this year)

Crane erecting 'U' trough sections at the down end

14 July 2018 11:30 AM
Viewed 157 times
(1 time this month, 157 times this year)