High Capacity Corridor Upgrade project

The High Capacity Corridor Upgrade project (previously the Cranbourne Pakenham Line Upgrade project) is being delivered by the Level Crossing Removal Authority to support the new High Capacity Metro Train (HCMT) fleet. The work includes track duplication on the Cranbourne line at Dandenong South, minor platform extensions, and the replacement of signalling, overhead wires and traction substations along the Cranbourne and Pakenham railway lines.

New overhead stanchions in place on the Dandenong tracks at Malvern station

26 April 2018 12:33 PM
Viewed 207 times, 56 times this year)

New rear view mirror added at the up end of Malvern platform 3

26 April 2018 10:18 AM
Viewed 199 times, 56 times this year)

New concrete bases for overhead stanchions at Malvern station

12 April 2018 10:27 AM
Viewed 203 times
(9 times this month, 75 times this year)

New concrete bases for overhead stanchions at Malvern station

12 April 2018 10:27 AM
Viewed 199 times
(5 times this month, 64 times this year)

New overhead stanchions in place where the works siding at Caulfield station once lay

13 March 2018 15:37 PM
Viewed 245 times
(1 time this week, 3 times this month, 78 times this year)

New stanchions in place at Oakleigh station, but the overhead wires have yet to be changed over

13 March 2018 13:27 PM
Viewed 1105 times
(1 time this week, 13 times this month, 856 times this year)

New overhead stanchions in place at Oakleigh, with new lengths of rail stockpiled between the tracks

13 March 2018 13:23 PM
Viewed 326 times
(3 times this week, 9 times this month, 119 times this year)

Co-acting signals 16P and 16 at the up end of Oakleigh platform 1

13 March 2018 13:20 PM
Viewed 307 times
(4 times this month, 76 times this year)

Platform extensions works at the up end of Oakleigh platform 1 and 2

13 March 2018 13:19 PM
Viewed 329 times
(4 times this week, 8 times this month, 100 times this year)

New overhead stanchions in place at Oakleigh, with new lengths of rail stockpiled between the tracks

13 March 2018 13:19 PM
Viewed 388 times
(3 times this week, 13 times this month, 110 times this year)

New overhead stanchions awaiting installation between Oakleigh and Huntingdale stations

13 March 2018 13:18 PM
Viewed 230 times
(4 times this month, 76 times this year)

Three additional traction power feeders in the new overhead at Huntingdale station

13 March 2018 13:14 PM
Viewed 245 times
(2 times this week, 5 times this month, 66 times this year)

New overhead stanchions and wire in place at Huntingdale station

13 March 2018 13:05 PM
Viewed 508 times
(2 times this week, 8 times this month, 125 times this year)

New overhead stanchions and wire in place at Huntingdale station

13 March 2018 13:05 PM
Viewed 474 times
(6 times this week, 13 times this month, 85 times this year)

Equipment ready to install new overhead stanchions between Oakleigh and Huntingdale stations

13 March 2018 13:04 PM
Viewed 217 times
(7 times this month, 85 times this year)

New overhead stanchions awaiting installation between Oakleigh and Huntingdale stations

13 March 2018 13:03 PM
Viewed 202 times
(3 times this week, 7 times this month, 65 times this year)

New overhead stanchions awaiting installation between Hughesdale and Oakleigh stations

13 March 2018 13:02 PM
Viewed 173 times
(6 times this month, 66 times this year)

New overhead stanchions awaiting installation between Hughesdale and Oakleigh stations

13 March 2018 13:02 PM
Viewed 208 times
(3 times this month, 72 times this year)

New stanchions in use supporting the overhead at Caulfield platform 3 and 4

13 March 2018 12:33 PM
Viewed 403 times
(5 times this month, 89 times this year)

Platform extension works at the up end of Caulfield platform 4

13 March 2018 11:20 AM
Viewed 238 times
(5 times this month, 82 times this year)

Temporary plastic signal trunking beside the tracks at Caulfield

13 March 2018 11:09 AM
Viewed 235 times
(1 time this week, 4 times this month, 64 times this year)

Works compound in the former goods yard at Malvern

13 March 2018 11:07 AM
Viewed 269 times
(1 time this week, 7 times this month, 84 times this year)

Down end of the Cranbourne line track duplication at Greens Road

13 January 2018 11:50 AM
Viewed 654 times
(5 times this week, 13 times this month, 211 times this year)

Track duplication along the Cranbourne line at the Dandenong Bypass

13 January 2018 11:46 AM
Viewed 424 times
(29 times this week, 32 times this month, 161 times this year)