Wongm's Rail Gallery » Melbourne railway traction substations

Melbourne railway traction substations

Scattered around Melbourne's suburban railway network, 68 traction substations convert 22,000V AC power supplied by electricity companies to the 1500V DC used by trains. The extension of suburban trains to South Morang and Sunbury will add four more. (a different source put the number in 2008 at 67 substations and 23 tie stations)

Underground traction power feeders to the Hampton Park tie station

24 March 2019 17:07 PM
Viewed 46 times
(46 times this month, 46 times this year)

Hampton Park tie station, provided with the 1995 electrification to Cranbourne

24 March 2019 17:06 PM
Viewed 25 times
(25 times this month, 25 times this year)

Remains of a 'Merz' stanchion base at the end of Flinders Street platform 7

31 January 2019 13:48 PM
Viewed 24 times
(3 times this month, 24 times this year)

New traction substation taking shape at the up end of Eaglemont station

20 January 2019 13:28 PM
Viewed 38 times
(10 times this month, 38 times this year)

Upgrade works at the Rosanna substation

20 January 2019 13:24 PM
Viewed 32 times
(10 times this month, 32 times this year)

Upgrade works at the Rosanna substation

20 January 2019 13:24 PM
Viewed 39 times
(1 time this week, 14 times this month, 39 times this year)

Overhead termination at Macleod platform 3

20 January 2019 12:43 PM
Viewed 36 times
(1 time this week, 8 times this month, 36 times this year)

Additional bracing applied to an overhead stanchion between Heidelberg and Eaglemont

20 January 2019 12:20 PM
Viewed 39 times
(2 times this week, 10 times this month, 39 times this year)

New traction substation taking shape at the up end of Eaglemont station

20 January 2019 12:18 PM
Viewed 44 times
(9 times this month, 44 times this year)

Timber platform beside the overhead sectioning switches at Alphington

20 January 2019 12:15 PM
Viewed 35 times
(2 times this week, 8 times this month, 35 times this year)

Traction power substation recently completed on the former Outer Circle reservation at Fairfield

Built alongside a tie station completed a few years earlier

20 January 2019 12:13 PM
Viewed 33 times
(10 times this month, 33 times this year)

Croxton substation, commissioned in 1962 with 1,500 kW capacity

20 January 2019 11:53 AM
Viewed 38 times
(10 times this month, 38 times this year)

New traction substation taking shape beside the existing tie station at Bell

20 January 2019 11:49 AM
Viewed 36 times
(11 times this month, 36 times this year)

New traction substation taking shape beside the existing tie station at Bell

20 January 2019 11:49 AM
Viewed 31 times
(1 time this week, 6 times this month, 31 times this year)

Hawkstowe substation, at the down end of the station

20 January 2019 11:16 AM
Viewed 28 times
(5 times this month, 28 times this year)

Keon Park tie station

20 January 2019 09:58 AM
Viewed 31 times
(1 time this week, 10 times this month, 31 times this year)

Reservoir substation: 1,500 kW capacity commissioned in 1963

Originally opened on electrification, fed by a 25 Hz supply with a pair of rotary converters providing 1,500 kW capacity

20 January 2019 09:55 AM
Viewed 25 times
(7 times this month, 25 times this year)

Clifton Hill tie station

20 January 2019 09:44 AM
Viewed 38 times
(11 times this month, 38 times this year)

Clifton Hill tie station

20 January 2019 09:44 AM
Viewed 27 times
(3 times this week, 11 times this month, 27 times this year)

Timber retaining wall around a stanchion at Jolimont

20 January 2019 09:38 AM
Viewed 34 times
(1 time this week, 10 times this month, 34 times this year)

Traction power feeders at the Laverton tie station

20 January 2019 08:00 AM
Viewed 36 times
(12 times this month, 36 times this year)

Circuit breakers and auxiliary transformers at the Altona Junction substation

20 January 2019 07:45 AM
Viewed 30 times
(1 time this week, 6 times this month, 30 times this year)

Traction power feeders on the Mernda line at Clifton Hill

28 December 2018 11:33 AM
Viewed 51 times
(5 times this week, 16 times this month, 51 times this year)

22 kV aerial feeders head underground at the up end of Alphington

28 December 2018 09:11 AM
Viewed 43 times
(7 times this week, 10 times this month, 43 times this year)

Viewed 8119 times (39 times this week, 98 times this month, 380 times this year)