Wongm's Rail Gallery » Metro Tunnel works at South Kensington

Metro Tunnel works at South Kensington

The western Metro Tunnel portal is located beside the Sunbury line at South Kensington

McLeod Rail hi-rail excavator at work shifting rail in the sidings at North Dynon

The sidings were relocated to make room for the power lines, which had to be moved to make room for the tunnel portal

27 June 2018 10:28 AM
Viewed 370 times
(2 times this week, 3 times this month, 58 times this year)

Trio of transmission line pylons at South Kensington, allowing the lines to be moved without shutting down power to the Melbourne CBD

22 April 2018 11:04 AM
Viewed 1031 times
(5 times this week, 10 times this month, 169 times this year)

Mobile crane erecting a new transmission line pylon at South Kensington

22 April 2018 11:04 AM
Viewed 437 times
(3 times this month, 83 times this year)

Drainage works at the down end of South Kensington station

20 February 2018 18:04 PM
Viewed 373 times
(1 time this month, 95 times this year)

Power line works at the down end of South Kensington station

18 February 2018 09:34 AM
Viewed 937 times
(1 time this week, 4 times this month, 128 times this year)

Power lines works at the down end of South Kensington station

18 February 2018 09:34 AM
Viewed 401 times
(1 time this week, 2 times this month, 80 times this year)

Excavation work alongside the railway embankment at South Kensington

16 February 2018 08:48 AM
Viewed 537 times
(1 time this week, 2 times this month, 81 times this year)

Piling works for a new transmission line tower at the down end of South Kensington station

9 February 2018 18:03 PM
Viewed 368 times
(8 times this month, 74 times this year)

Erecting a new transmission line tower at the down end of South Kensington station

9 February 2018 09:19 AM
Viewed 369 times
(1 time this week, 5 times this month, 74 times this year)

Erecting a new transmission line tower at the down end of South Kensington station

6 February 2018 17:53 PM
Viewed 377 times
(3 times this week, 12 times this month, 116 times this year)

Erecting a new transmission line tower at the down end of South Kensington station

6 February 2018 10:39 AM
Viewed 403 times
(5 times this month, 90 times this year)

Building the new high voltage transmission lines at South Kensington

2 February 2018 09:01 AM
Viewed 409 times, 112 times this year)

Steel foundations in place for the relocation of high voltage transmission lines at South Kensington

25 January 2018 11:57 AM
Viewed 348 times
(2 times this week, 3 times this month, 91 times this year)

Soil nailing works underway at the down end of South Kensington station

23 January 2018 09:19 AM
Viewed 365 times
(2 times this week, 4 times this month, 98 times this year)

Steel foundations in place for the relocation of high voltage transmission lines at South Kensington

19 January 2018 09:02 AM
Viewed 380 times
(1 time this week, 4 times this month, 95 times this year)

Pouring foundations for the relocation of high voltage transmission lines at South Kensington

15 January 2018 08:43 AM
Viewed 410 times
(1 time this month, 89 times this year)

Completed foundations for the relocation of high voltage transmission lines at South Kensington

5 January 2018 08:53 AM
Viewed 364 times
(1 time this week, 13 times this month, 97 times this year)

Pouring foundations for the relocation of high voltage transmission lines at South Kensington

29 December 2017 09:05 AM
Viewed 383 times, 104 times this year)

Soil nailing works underway at the down end of South Kensington station

4 December 2017 12:17 PM
Viewed 347 times, 86 times this year)

Piled foundations ready for the relocation of high voltage transmission lines at South Kensington

27 November 2017 18:03 PM
Viewed 365 times
(1 time this week, 1 time this month, 83 times this year)

Piled foundations ready for the relocation of high voltage transmission lines at South Kensington

14 November 2017 09:00 AM
Viewed 405 times
(1 time this week, 3 times this month, 3 times this year)

Piled foundations ready for the relocation of high voltage transmission lines at South Kensington

23 October 2017 18:00 PM
Viewed 374 times
(1 time this week, 1 time this month, 6 times this year)

Piles foundations ready for the relocation of high voltage transmission lines at South Kensington

21 October 2017 17:52 PM
Viewed 317 times
(3 times this week, 3 times this month, 8 times this year)

Piling rig ready to work relocating high voltage transmission lines at South Kensington

17 October 2017 08:41 AM
Viewed 446 times
(4 times this month, 14 times this year)
Tags

Viewed 1136 times (3 times this week, 4 times this month, 301 times this year)