Wongm's Rail Gallery » Furlong Main level crossing removal project

Furlong Main level crossing removal project

In 2015 work commenced on the grade separation of the Main Road level crossing at St Albans station, with the Furlong Road level crossing at Ginifer station later being added to the project scope.

'Pit' marking spray painted between the platform tracks at St Albans station

Tuesday 6 December 2016 8:01 AM
Viewed 581 times
(4 times this month, 4 times this year)

Additional soil nailing in the cutting walls at the up end of St Albans, now covered with shotcrete

Tuesday 6 December 2016 7:59 AM
Viewed 663 times
(3 times this month, 3 times this year)

Section of in-situ concrete retaining wall between shotcreted soil nailed walls

Tuesday 6 December 2016 7:59 AM
Viewed 1246 times
(8 times this month, 10 times this year)

Transition between in-situ concrete and shotcreted soil nailed retaining walls at the up end of St Albans

Tuesday 6 December 2016 7:59 AM
Viewed 779 times
(3 times this month, 4 times this year)

Pile of dismantled formwork at the up end of St Albans station

Tuesday 6 December 2016 7:58 AM
Viewed 552 times
(8 times this month, 8 times this year)

Pile of dismantled formwork at the up end of St Albans station

Tuesday 6 December 2016 7:58 AM
Viewed 510 times
(2 times this month, 2 times this year)

Work on the ramps at Ginifer platform 1 has progressed following the recent weekend occupation

Tuesday 6 December 2016 7:57 AM
Viewed 549 times
(2 times this month, 2 times this year)

Work on the ramps at Ginifer platform 1 has progressed following the recent weekend occupation

Tuesday 6 December 2016 7:57 AM
Viewed 555 times, 0 times this year)

Work on the shelters at Ginifer platform 2 has progressed following the recent weekend occupation

Tuesday 6 December 2016 7:57 AM
Viewed 565 times
(1 time this month, 1 time this year)

Cutting walls cleaned up at the up end of Ginifer station

Tuesday 6 December 2016 7:56 AM
Viewed 456 times
(1 time this month, 1 time this year)

Metal baskets stacked between Albion and Ginifer stations

Tuesday 6 December 2016 7:55 AM
Viewed 480 times
(2 times this month, 2 times this year)

Ramp and shelters waiting installation to Ginifer platform 1

Saturday 3 December 2016 10:17 AM
Viewed 528 times
(1 time this month, 1 time this year)

Future car park site on the east side of Ginifer station

Saturday 3 December 2016 10:17 AM
Viewed 572 times
(2 times this month, 2 times this year)

Tertiary bonding of the overhead lines at Ginifer station

Due to the metal stanchions being tied electrically to the cutting walls, additional insulation is required between them and the overhead wires.

Saturday 3 December 2016 9:27 AM
Viewed 694 times
(3 times this month, 3 times this year)

Tertiary bonding of the overhead lines at Ginifer station

Due to the metal stanchions being tied electrically to the cutting walls, additional insulation is required between them and the overhead wires.

Saturday 3 December 2016 9:27 AM
Viewed 646 times
(3 times this month, 3 times this year)

Tertiary bonding of the overhead lines at Ginifer station

Due to the metal stanchions being tied electrically to the cutting walls, additional insulation is required between them and the overhead wires.

Saturday 3 December 2016 9:26 AM
Viewed 581 times
(1 time this month, 1 time this year)

Future car park site on the east side of Ginifer station

Saturday 3 December 2016 9:08 AM
Viewed 558 times
(3 times this month, 3 times this year)

Ruth Street pedestrian bridge closure notice - due to reopen at the end of October!

Tuesday 22 November 2016 9:56 AM
Viewed 488 times
(2 times this month, 2 times this year)

Ruth Street pedestrian bridge closure notice - due to reopen at the end of October!

Tuesday 22 November 2016 9:55 AM
Viewed 517 times
(1 time this month, 1 time this year)

Work stalled at the Ruth Street pedestrian bridge

It was due to open to the public at the end of October

Tuesday 22 November 2016 9:55 AM
Viewed 498 times
(1 time this month, 1 time this year)

Stairs and ramps now in place at the stalled Ruth Street pedestrian bridge

It was due to open to the public at the end of October

Tuesday 22 November 2016 9:51 AM
Viewed 550 times, 0 times this year)

Stairs and ramps now in place at the stalled Ruth Street pedestrian bridge

It was due to open to the public at the end of October

Tuesday 22 November 2016 9:51 AM
Viewed 681 times
(1 time this week, 2 times this month, 2 times this year)

Diesel powered portable pump parked at the north end of the rail cutting at St Albans

Tuesday 22 November 2016 9:50 AM
Viewed 466 times, 0 times this year)