Wongm's Rail Gallery » Track machines

Track machines

Pictures of ballast tampers, ballast plows, sleeper wagons, rail layers, overhead wiring trucks, rail grinders and other trackwork machinery and trains

Ballast cleaners

January 16, 2016

Ballast cleaners are used to remove spoil from the trackbed

Ballast compactor

November 16, 2007

Ballast ploughs

March 27, 2009

Placed on the end of ballast train, they level off the dropped gravel

Ballast regulator

October 29, 2015

A smaller track machine used to level out and shape ballast after a tamper has packed it down

Ballast tampers

October 29, 2015

Use tines to pick ballast under and around the sleepers - 'lift and 'line' the track, correcting faults by packing 'tamping' under the sleepers

Ex-V/Line equipment from South Dynon freight terminal

June 06, 2009

Two doodads marked for scrap at South Dynon:

In V/Line orange is an internal transfer vehicle, purchased in 1989/1990 to shift containers around at the South Dynon Container Terminal. Unlike normal trailers it doesn't have twistlocks, the containers are just dropped into place. It has the number '6-61-001' on the side, which puts it with various other Victorian track machines that have numbers in the format.

In yellow are two Malcolm Moore lifting units that were part of the original container cranes at South Dynon. Each unit was secured to the lifting shaft on the gantry by chains, the lifting unit went up, down, sideways and could turn at least 180 degrees. The crane ran on the crane rails the total length on the operating area being around 700 metres. Either 20', 30' or 40' containers could be top lifted. Also four calliper lifting arms can be swung out and down to line up with the lifting pockets on 'bottom' lift units. Originally 6 'yellow cranes' were built for NSW in the 1970's for the Enfield container terminal, which was later cancelled, hence a pair were bought by the PTC.

Hi-rail excavators

August 08, 2015

Various excavators fitted with rail wheels for operation on railway lines, often with specialised equipment on the ends of their booms

Hi-rails

April 30, 2014

4x4s and other motor vehicles used for track inspection and maintenance

MVM Rail track layer

May 16, 2011

Used to lay new track on a prepared base, the machine lays down concrete sleepers as it moves along

Overhead line maintenance

February 10, 2015

Various hi-rail trucks are used to get works crews close enough to the overhead lines for maintenance.

Rail flaw detector

October 10, 2015

Operated by Speno Australia, this hi-rail Unimog truck uses ultrasound to examine rails to find any flaws in them. The operator sits in the back, looking out over the sensor unit towed behind. It is usually escorted by a hi-rail escort in front and behind

Rail grinder RR24M30

February 26, 2011

Operated by Speno, it is a gauge convertible 24 wheel grinder. I found at North Geelong Yard on the broad gauge, it has been working over the Melbourne suburban network in late 2009 and again in mid 2010. It has also run on narrow gauge. I have numbered the bits from the power / generator unit end

Rail grinders

July 20, 2012

Rail grinders are used to restore the profile and remove irregularities from worn rails. There are 3 visiting Victoria from time to time - all operated by John Holland / Loram. RG9 is the newest and is on the standard gauge, RG8 is a truck towing grinding units, and RG7 is the oldest.

Rail miller

March 22, 2016

The Linsinger Austria SF02-W-FS rail milling machine is used across the broad gauge rail network in Victoria, often to correct rail profile issues that result in level crossings not activating

Rail threader wagon CFCF 1

July 04, 2014

Coded CFCF 1 with John Holland stickers on the side, this wagon is used on the end of rail trains in order to discharge long lengths of new rail from the flat wagons onto the ground. It was built from a CFSX / VZSX sleeper discharge transporter wagon, which itself was built on a VLCX underframe.

Rail welding

November 11, 2007

Thermite welding is used to join rails together in the field. Everything comes in a kit, with packing up around the joint, then the crucible or pot put above the joint, and lit up. Molten metal flows out the bottom, which is left to cool. The packing is removed, and then the joint is ground smooth.

Sleeper discharge

May 27, 2010

Wagons used to transport sleepers to where they are required. Some wagons use a small tractor to discharge the sleepers onto the ground.

Tie cranes

March 20, 2008

Excuse the Americanism, these are small rail mounted cranes used to lift and place replacement sleepers into existing lines. They often have a small trolley that goes along for the ride to carry the actual sleepers

Tube Cube

February 08, 2013

The 'Tube Cube' is a vacuum excavator mounted to road-rail excavator, designed to excavate between and below sleepers without moving or disturbing track components.

VR crane 31

March 18, 2009

Stored at Spotswood for years pending eventual preservation, due to the cost of moving it elsewhere, the crane was scrapped in March 2009

Tags

Viewed 12232 times (10 times this week, 11 times this month)